Construction Works for Clarifiers and Filtration Units – Deir Mawas Water Treatment Plant
This project involves civil construction works for the clarifiers and filtration buildings at the Deir Mawas Water Treatment Plant. The scope includes:
- Casting of exterior walls for Clarifier No. 2
- Formwork removal for the exterior wall of Clarifier No. 1
- Steel reinforcement works for exterior and interior clarifier walls
- Interior wall carpentry for the clarifier units (June 3, 2022)
- Ongoing concrete casting for interior walls of the clarifier building
- Sloped concrete floor casting in the underground storage tank
- Formwork for the roof slab of the pipe gallery in the filtration building
- Surface preparation and waterproofing works beneath the filter structure
- Continuous carpentry and casting work across clarifier and filter units
These works are part of a broader infrastructure development plan to improve drinking water treatment capacity and system durability in Deir Mawas.